Job Details

Your next big opportunity awaits

Drilling and Installation of Boreholes in Schools

Plan International Zambia | Eastern Province & Central Province

Plan International Zambia

Innovating the future of tech solutions in Zambia.

Job Description

Plan International Zambia is an international non-governmental organization that strives for a just world that advances children’s rights and equality of girls. Our strategic goal is to make significant contribution to vulnerable and excluded adolescent girls to reach their full potential.

In order to achieve the goal, Plan International Zambia (PIZ) through the Eastern and Central Program Area is implementing a project called BRECS (Building Resilience through Climate Smart Sustainable Livelihoods). The (BRECS) project, implemented by Plan International in collaboration with Jesus Cares and Diaconia, aims to enhance the capacity of communities in Central and Eastern Zambia respectively, to adapt and build resilience to the impacts of climate change by focusing on green enterprises, sustainable farming practices, hydroponics systems in schools, protection of children and young people, and promoting women’s access to resources and decision-making.

The boreholes will supply water to the hydroponics using the deep culture method and to the dug-out fishponds to support fish production in the schools.

1.     Objectives of the Activity

a)    To conduct hydrogeological surveys to identify viable water sources in 6 schools in Eastern and Central Province to support the hydroponics and aquaponics.

b)    To drill and equip boreholes in selected schools.

c)     To install 2,500-liter water tanks on 6-meter-high stands for water storage and distribution to support fish ponds and hydroponics.

2.     Scope of Work

The contractor will be responsible for the following tasks:

a) Preliminary Assessment and Survey

b) Borehole Drilling in close collaboration/ monitored by the Ministry of Local Government  and Ministry of water development and sanitation

c) Borehole Equipping

d) Water Tank Installation

3.     Deliverables

4.     Timeframe

5.     Site Locations

Lot 1

Chowa Panga Secondary School- Central Province

St. Paul’s Boys Secondary School- Central Province

Lot 2

Chadiza Boarding  Secondary School- Eastern Province

Chanjowe Day Secondary School- Eastern Province

Mbande Day Secondary School- Eastern Province

Mbozi Day Secondary Schools- Eastern Province

Plan International Zambia reserves the right to split the contract award based on Lots and/or award to one contractor

6.     Supervision and Reporting

7.     Project Completion

Upon completion of the installation, the boreholes should meet the specified dimensions and standards.  Completion certificate of installations to be done accompanied by report from local authority. A handover should be organized.

8.     Other terms and conditions

a.     The contractor shall undertake a comprehensive hydrogeological survey and submit findings for approval prior to drilling. The survey must guide borehole siting.

b.    The contractor shall be solely responsible for borehole siting based on a hydrogeological study. Plan International Zambia shall not be liable for non-productive or dry boreholes resulting from inadequate siting.

c.     A borehole shall be deemed ‘dry’ if it yields less than 0.5 cubic meters per hour during a standardized pump test lasting at least 4 hours

d.    In the event that a borehole is determined to be dry, no payment shall be made for drilling activities related to that borehole.

e.     Should a borehole be deemed dry, the contractor shall, at their own cost, drill an additional borehole within the same vicinity, subject to new siting and Plan International Zambia, Local Authority Engineer and  Department of Water Affairs Engineers  approval.

9.     Warranty

12 months warranty on pumps and installed equipment.

10.  Evaluation Criteria :

Administrative requirements

Failure to submit all documents above will lead to disqualification

Technical Requirements (70 POINTS)

Financial Proposal (30  POINTS)

Price Competitiveness (30pts)

TOTAL: 100PTS

The vendor(s) with the highest scores shall be considered for award

All submission for this tender should be addressed to:

The Supply Chain & Administration Manager

Plan International Zambia
St Eugene Office Park, Plot: #2866
Ibex Hill, Off Leopards Hill Road
Private Bag 518X RW

All bid Submissions should be [email protected]  by 17:00hrs CAT on 28th  August 2025. Any submission received after the deadline will not be considered.

All clarifications must be sent to : [email protected]. All clarifications must be received by 21st August 2025. Responses to the clarifications will be sent to all bidders by 17:00hrs on 22nd August 2025.

“Women-owned, led and influenced companies’ are encouraged in this tender.”

Don't miss out on this opportunity!